Resource Assignments Page of the Integration Wizard-Primavera
Use this page to define how budgeted and forecast resources and their respective spreads are imported into the Cobra project from the schedule.
Budget
This group box is enabled only if you select the Load budget resource assignments option on the Date Selection page of the Integration Wizard.
Field | Description |
---|---|
Default budget class | Select the budget class to import the budget into. Use this option in conjunction with the other class options on this page.
Click to select a Cobra budget class. |
Load all budget into default class | Select this option to import all resource assignments into the same class in Cobra. If you select a control account-level class, only the resources of activities mapped to the control account are imported.
If there is a work package mapped on the Schedule Mapping page and a value is found in the associated schedule field in an activity, resources assigned to the activity are not imported into a control account-level budget class. |
Load budget class from field | Select this option to inform Cobra that a schedule field is assigned a class value. When you select this option, the lookup is enabled.
Click to select a code field, user character field, text field, or cost class on the assignment in the schedule. The schedule field selected can be used to load Control Account and Work Package classes at the same time. This lookup is not displayed for import files since the field selection determines where the classes are loaded from. |
Load only these budget classes | This field is enabled if you select the
Load budget class from field option and select a value for it. Selecting a value in this field informs Cobra to filter the data being imported to only those activities or resource assignments with the selected class. If this field is blank, all data is imported.
Click to select the class to be imported. During the import, Cobra imports assignment records only if they match the selected classes. |
Forecast
This group box is enabled only if you select the Load forecast resource assignments option on the Date Selection page of the Integration Wizard.
Field | Description |
---|---|
Default forecast class | Select the forecast class to import the forecast into. Use this option in conjunction with the other class options on this page.
You can load data into both the budget and forecast in one import. This is useful when a new work is being added to the project. And this time, the forecast and the budget are the same. If the import contains forecast data in period before the status date, those records are ignored (not loaded) and there is no warning in the process log. Click to select a forecast class in the Cobra project or template. This forecast class is used if no schedule class is defined, or if it is blank. |
Load all forecast into the default class | Select this option to import all resource assignments into the same forecast class in Cobra. If you select a control account-level class, only the resources of activities mapped to the control account are imported.
If there is a work package mapped on the Schedule Mapping page and a value is found in the associated schedule field in an activity, resources assigned to the activity are not imported into a control account-level forecast class. |
Load forecast class from field | Select this option to inform Cobra that a schedule field has been defined with the class value.
The corresponding field is enabled when you select this option. Click to select a code field, user character field, or cost class on the assignment in the schedule. The schedule field selected can be used to load control account and work package classes at the same time. The Lookup dialog box is not displayed for import files since the field selection determines where the classes are loaded from. |
Load only these forecast classes | This field is enabled only if you select the Load forecast class from field option and select a value for it. Selecting a value in this field informs Cobra to filter the class being imported only to the selected classes. If this field is blank, all classes found in the selected schedule field are imported.
Click to
select from the distinct values in the selected schedule field where the class is to be imported from.
Note: During integration, Cobra imports assignment records only if they match the selected classes. If the class value being loaded from the schedule is empty, Cobra uses the default class.
|
Replace existing forecast | When this option is selected, Cobra performs the following actions:
This option displays when importing into an existing project. |
Add to existing forecast | Select this option to inform Cobra to add any imported values to those that already exist in the corresponding classes in Cobra.
|
Allow loading forecast in the current status period | Select this option to allow time-phased spread values to be loaded in the current status period during integration.
Attention: For more information, see
Integration Wizard Preferences.
|
Contents
Field | Description |
---|---|
Calculate apportionment | Select this option to enable the Define Calculation button. |
Define Calculation | Click this button to display the Calculation Range and the Classes pages of the Calculate Apportionment Wizard. Selecting this option informs Cobra to perform the apportionment calculation after the import process is complete.
After importing the project into Cobra, the apportionment calculation runs and adds any apportioned resources to the project based on the defined apportionment mapping. Click Next on the Classes page to return to the Resource Assignment page of the Integration Wizard. This button is enabled only if apportionment mappings are defined for the selected Cobra project. |
Retrieve Quantity for: | Use this field to specify where to retrieve resource quantity values when importing from Primavera.
Your options are:
Note: You can select one or more options.
Selected resource types will load Quantity values for the matching Primavera resource types, while cleared resource types will load Cost values for the matching Primavera resource types. |
Load daily time-phased data | This option is enabled if the Primavera API location has been specified in the
Connection Information dialog box of the Integration Wizard.
By default, this option is cleared. Cobra reads the total Resource Assignment Cost or Units from the Primavera database and spreads the values using a linear spread. If this option is selected, the daily time-phased spread values are extracted from the Primavera database using the Primavera API. Cobra will use the Resource Assignment spread profile from the extracted data when loading the spread in Cobra. |